Delayed processes can really hit the bottom line, according to Sandy Hamby of MOCA Systems.

MOCA Systems, Inc. recently used data from the Touchplan® production planning platform to analyze over 321,042 committed activities over the last 12 months to identify

Production planning platform Touchplan recently released a report that identifies the top five causes of construction delays, according to ConstructionDive.

Variance reasons are explanations for why a planned activity that was committed to finish on a certain date was not completed as planned….Variances related to

Touchplan users provided reasons for delays whenever tasks finished late on the platform. The platform captured data from over 321,000 scheduled construction tasks over the