New Study: Top 5 Factors Impacting Construction Project Schedules
MOCA Systems Inc recently used data from the Touchplan® production planning platform to analyze over 321 042 committed activities over the last 12 months to
MOCA Systems Inc recently used data from the Touchplan® production planning platform to analyze over 321 042 committed activities over the last 12 months to
Production planning platform Touchplan recently released a report that identifies the top five causes of construction delays according to ConstructionDive
Variance reasons are explanations for why a planned activity that was committed to finish on a certain date was not completed as planned Variances related
A persistent labor shortage combined with ongoing supply chain uncertainty can greatly increase the risks of construction project delays accidents and litigation It has never
By synchronizing the Critical Path Method with the Last Planner System® using Touchplan and P6 Jacobsen Construction efficiently managed the complexities of building Utah s
Weather and the effects of climate change may affect construction productivity and real estate development more than people think