CES 2025: How To Meet AI’s Inexhaustible Demands For Power
With billions being invested in data center construction, the need for efficient planning, collaboration, and sustainable solutions has never been more important.
INDUSTRY PERSPECTIVES
With billions being invested in data center construction, the need for efficient planning, collaboration, and sustainable solutions has never been more important.
Delayed processes can really hit the bottom line, according to Sandy Hamby of MOCA Systems.
MOCA Systems, Inc. recently used data from the Touchplan® production planning platform to analyze over 321,042 committed activities over the last 12 months to identify
Production planning platform Touchplan recently released a report that identifies the top five causes of construction delays, according to ConstructionDive.
Variance reasons are explanations for why a planned activity that was committed to finish on a certain date was not completed as planned….Variances related to
Touchplan users provided reasons for delays whenever tasks finished late on the platform. The platform captured data from over 321,000 scheduled construction tasks over the