New Study: Top 5 Factors Impacting Construction Project Schedules
MOCA Systems, Inc. recently used data from the Touchplan® production planning platform to analyze over 321,042 committed activities over the last 12 months to identify
MOCA Systems, Inc. recently used data from the Touchplan® production planning platform to analyze over 321,042 committed activities over the last 12 months to identify
Variance reasons are explanations for why a planned activity that was committed to finish on a certain date was not completed as planned….Variances related to
Touchplan users provided reasons for delays whenever tasks finished late on the platform. The platform captured data from over 321,000 scheduled construction tasks over the
A persistent labor shortage combined with ongoing supply chain uncertainty can greatly increase the risks of construction project delays, accidents, and litigation. It has never
By synchronizing the Critical Path Method with the Last Planner System® using Touchplan and P6, Jacobsen Construction efficiently managed the complexities of building Utah’s tallest
Weather and the effects of climate change may affect construction productivity and real estate development more than people think.