Search Touchplan website:

4 Tips for a Zero-Punch-List Project

Getting to the end of a project only to tackle hundreds of punch-list items is anything but satisfying. Punch lists, or lists of work that needs to be redone, typically result from some kind of process failure during the project. Generally, a punch list item is work that wasn’t done correctly the first time, or that was damaged by other work that was done afterwards to the extent that it doesn’t meet standards.

While most people accept punch lists as a necessary evil, they’re more avoidable than you might think. Read on for four tips from Lean construction expert Hal Macomber on how to run your projects in a post-rework world.

1. Define Acceptance Criteria Early

Make it a practice to establish a benchmark for each task the first time it’s performed. A benchmark is set by having each type of work inspected the first time it’s done to ensure that it’s acceptable to the architect before the work continues. The benchmark then serves as a visual standard for the team to reference going forward. “It depends on the project, but if you have eighty-four rooms and you benchmark the first one, you can avoid all the mistakes you made on the first one in the eighty-three additional units. So it’s possible that you could build eighty-three units without rework associated with standard,” says Macomber.

2. Foster a “Customer Mindset”

If you can get your teams to view on another as customers, the entire mindset of the project changes. When people see the next trade in line as their customer—rather than the eventual occupant of the building—the need to optimize the use of the space becomes more immediate, as does the obligation to protect one another’s work. “Get people to treat each other’s work with respect, treat each other as customers and ensure that you are not going to make work for other people, just like you don’t want other people to make work for you,” advises Macomber.

3. Look for Patterns

One way to preemptively minimize punch list items is to look for systemic patterns that may be causing issues on your project. Macomber offers an example: “If a procurement was held up because a submittal took too long to get approved by the architect, engineer and owner, the likelihood that the next submittal that goes through the process will also be late could be very high.” Noticing problematic patterns and addressing them early on at the system level will greatly minimize your punch list.

4. Address Punch List Items Daily

Along the same lines, punching your list (figuratively speaking) early and often is important. By waiting until an entire floor is finished, for example, you increase the likelihood of having to do the same type of rework multiple times. “If someone took a shortcut, they probably didn’t take it once. They probably took it as many times as they had to do that task,” says Macomber. Set a benchmark as early as possible to avoid having to fix the same mistake multiple times later on.

Macomber recommends daily punch lists for maximum efficiency. “Often people think that a zero-punch-list project means that you punch as you go so that when you get to the certificate of occupancy, you’re done. But that’s not what we mean by zero-punch-list project. We mean you didn’t have anything to punch in the first place.”

 

Touchplan on Best Construction Project Management Software List

Touchplan has been named one of user review site G2 Crowd’s “13 Best Construction Project Management Software Solutions in 2019.” G2 Crowd collects objective reviews from users of a variety of business technologies to enable customers to easily find a solution that meets their needs.

All reviews are written by verified users of the product, and must answer a set of specific questions regarding their experience. The site’s review model allows technology buyers to research beyond analyst reports or vendor-supplied materials so that they can purchase with greater confidence and a higher chance of satisfaction in their choice based on information provided by industry peers.

Currently ranked third on the list, Touchplan scored 4.1 out of 5 stars across its user reviews. According to a featured review, “Touchplan has made it so that we can ask our subcontractors/vendors for input on building their tasks into our overall project schedule. They prep this information ahead of time and we can all sit down together to build our schedule. It’s a very Lean process and has eliminated the need for us to transcribe information from conference room walls into a digital format: the record schedule is being created in real time.”

Another featured review shared tips for success, advising users to “Ensure that everyone stays involved. Hold weekly meetings or even morning standing meetings to make sure everyone checks in and is on track. Make sure that this technical [product] is compatible with the personnel that you have. If they are unwilling to use the computer and quickly check things complete, etc., then you will be unsuccessful.”

Having previously been designated a “High Performer” for Winter 2019, this is the second distinction Touchplan has received from G2 Crowd since December.

Senior Customer Success Manager Josie Cutts

“We’re thrilled to see our customers confirming the value they get from using Touchplan. To achieve this ranking as a five-year-old company tells us that we’re on the right track as we work to improve the way projects are planned and executed,” said Josie Cutts, Senior Customer Success Manager at Touchplan.

 

 

 

 

 

4 Ways to Improve Projects Using Digital Platforms

Thinking about using technology to step up your project planning? Many contractors have amplified the benefits of a Lean or Last Planner® approach through the use of digital tools. Here’s a rundown of how your projects will change, and tips to set you up for success from industry expert Hal Macomber.

1. Identify a Guide

“The first thing that you need to be successful in both analog and digital settings is someone who knows how to use the Last Planner System®. Somebody needs to know what they should be doing. What does success look like? You must have somebody who knows what it looks like when it’s happening. It’s always easier if the team has experience. But one person on the team who is recognized as being knowledgeable is sufficient. Just let that person lead.”

2. Improve Faster

“There are some very practical aspects of why your first weekly work plan needs to be digital. All the calculations are done for you. All statuses can be distributed. You don’t have to be chasing people around. They have tablets, they can tell you that they finished or they didn’t finish. Right off the bat, you have a far better chance that you’re going to get a good report on percent plan complete (PPC). I don’t mean that it’s going to be high PPC, I mean it’s going to be an accurate reporting of what happened, and that you’re in a position to share that promptly and to improve on that.

If you don’t have the data, you can’t improve right away. Digital tools immediately give you the data. So, from the beginning, you can make data-informed improvements from week two.”

3. Change the Dynamics

“Another key to making the Last Planner System® work is to shift the relationships of last planners to each other. We get high PPC and good flow when we have trade partner foremen treating each other as partners, as customers. How does software help this happen? The principal way is in the always-available visual display of the customer-performer relationships in the promise period. Nobody is able to do that when they’re analog. But if you start with digital, you get there in week one.”

4. Get Real-Time Data

“The latency in the analog approach makes the data less useful. Even when we get it, we’ve already gone on to different work. Eliminating that latency makes the data much more valuable. It’s much more like driving with a dashboard. What you’re looking at on the dashboard is useful while you’re driving, as opposed to calculating the miles per gallon of the last 100 miles you’ve driven. The usefulness of data is dramatically diminished by the latency, and you don’t even get the data if you didn’t put in the administrative effort. But with digital tools, all that latency goes away. And you get the benefits from that on day one.”

 

Touchplan Vlog: Why Your Project Needs Real-Time Updates

It’s inevitable that your schedule on any project will be subject to changes, but is everyone getting the same accurate information? Too often, teams aren’t notified in a consistent manner when there’s been an update to the project, resulting in confusion, delays and even disputes. The larger the project, the more of an issue this is likely to become. Watch the video below to learn how enabling your team to stay on track through real-time project updates will help you hit your project deadlines.

Continue reading “Touchplan Vlog: Why Your Project Needs Real-Time Updates”

How Make Ready Planning Can Make — or Break — Your Project

You have the right team in place, the materials have arrived on time, and even the weather is cooperating. “What could go wrong?” you think to yourself as the steam rises from your coffee in a perfect arc. And yet, three months later, the project is behind schedule, over budget, and no one even has time for coffee. How did this happen?

Incomplete or nonexistent make ready planning has derailed many projects, and yours is simply the latest casualty. Make ready planning (also called look-ahead planning) is a crucial step in the Last Planner® System between a pull phase plan and the weekly work plan. The aim is always to produce flow for every phase of work. When work is ready for people and people are ready for work, you get good flow and good productivity. The CM or GC’s superintendent (or a designee) is responsible for making work ready.

When you establish a pull phase plan, you’re establishing what the team says should be done. When you create the weekly work plan, you’re saying what you will do. But just because you should be able to do something doesn’t mean that you can do something, which can lead to promises being made that aren’t fulfilled. Make ready planning is designed to prevent this by taking time to establish what can be done and identify constraints.

During this step, the building process is broken down into specific operations or collections of operations, if it’s possible to do more than one at a time. These operations are broken down further into smaller tasks that can be promised individually. Planning at this granular level also identifies any safety and permitting issues that may need to be resolved.

Types of Constraints

There are three major types of constraints that are systematically uncovered during make ready planning. The first type is a directive, which involves getting direction from another party. Permits, RFIs and submittal approvals are all examples of directives.

The second type is a resource constraint. A resource is defined as anything that carries a load, and can include equipment, people, tools or space. “If you’re working in an electrical closet overhead, how many people can work in electric closet overhead? Maybe only one person. That space carries the load of one person,” explains Lean consultant Hal Macomber.

The third type of constraint is materials and prerequisite work. Material constraints are considered resolved when the material is purchased and promised for delivery on time. Increasingly, “on time” is defined as “just-in-time” delivery in which materials are only delivered shortly before installation in order to avoid wasting space, handling the material multiple times and disrupting the jobsite.

Plan Ahead

In order to have time to deal with any constraints identified, make ready planning should be completed well in advance of the work. “The creators of the Last Planner® System said we do this on at least a six-week horizon,” says Macomber.

When make ready planning isn’t performed with enough lead time, or is skipped entirely, constraints are usually identified too late to be addressed without causing delays or rework. If teams take for granted that a project will go according to plan and go directly from pull planning to regular work planning, they risk unforeseen delays and complications.

If you’re not sure whether you’ve done make ready planning, there’s an easy way to check. “If you’re talking about processes versus operations or some small collection of operations, the work’s not ready,” says Macomber.

Ready to start gaining on your schedule again? Invest time and thought in make ready planning and you’ll see the results you’re after.

Creating Community Through Affordable Housing in San Diego

Building is something Touchplan users excel at, and in providing them with technology that enables them to work more efficiently, our focus is usually on the the technical aspects of construction: how to identify constraints, meet deadlines, work safely and finish early. While this focus on efficiency and success is important, what’s really amazing is what our clients are building in addition to a structure of concrete, steel, wood or brick. What isn’t shown on a project plan is what is created when the trucks wheel away, the dust settles and the site fencing is replaced by landscaping—community.

Continue reading “Creating Community Through Affordable Housing in San Diego”

Building Leadership: A Q&A with Dr. Barbara Jackson

I recently spoke to Dr. Barbara Jackson, Director of the Franklin L. Burns School of Real Estate and Construction Management at the Daniels College of Business at the University of Denver. To follow up on her recent talk at Procore’s Groundbreak 2018, I wanted to hear her perspective on the AEC industry, its leadership and current challenges, and what she sees in its future. Our conversation has been lightly edited.

Continue reading “Building Leadership: A Q&A with Dr. Barbara Jackson”

Takt Time Planning and Laws of Production: Getting the Most Out of LPS®

Katherine Van Adzin: Hi, everyone! Let’s start off this week with a brief introduction to our guest, Colin Milberg. Colin, tell us about yourself.

Colin Milberg: I am a Lean construction consultant. I’ve been involved in Lean construction since roughly 2000, when I left my job on the Big Dig to go study with Iris Tommelein and Glenn Ballard at UC Berkeley, and I’ve been involved in my Lean journey ever since. I was part of the faculty at San Diego State University, and then I decided that the industry was more in dire need of this education than the students coming out, because they were just getting corrupted going into a corrupted industry. My services would be better rendered and my skills would be better rendered working directly with industry, which is how I moved to consulting. I’m also an instructor in the AGC CM Lean certification program.

KV: Thanks for the background, and we’re glad you can join us today! Hal, could you start us off with a definition of takt time?

Hal Macomber: Okay. Takt time comes from the German word, “takt.” It basically means beat, meter or pace, it’s like a metronome or the pace that a group is playing at. In the case of a production setting, whether it’s construction or it’s manufacturing, the pace is the time between operations. That’s what you’re talking about when you’re saying a pace. On a production line it could be that you get fifty-six seconds to install a steering wheel and then someone gets fifty-six seconds to do the next step in the line. Takt time at Toyota is established based on the rate at which they sell the product on that line, so they establish a pace based on sales rate, but that doesn’t have to be the case. You can establish pace based on other goals. The intent, though, is that you design your production approach to a consistent pace. And we’ll get into why that’s the situation as we explore the production laws.

KV: In a case where takt time isn’t tied to the pace of sales, is it tied to demand for the use of the space by other teams?

CM: The demand of space by others is determined by what you come up with for your takt time. You back into the takt time that you want to try to achieve. Part of that is a discussion of logistics and a bunch of other stuff, which we can get into when we get into the production laws. But once the takt time is established, that is what creates the demand from one step to the next.

HM: For the built environment, there is a promise to turn over space. If you’re doing a middle school, you might turn over classrooms before you turn over gymnasiums, or before you turn over something else. But you are starting with some kind of delivery of the product. In our case, it’s usually a whole building, or for a roadway, one lane of traffic.

Take the the Longfellow Bridge connecting Boston with Cambridge, for example. They had established a turnover date of one lane of traffic at a certain point in time, but they didn’t meet it because they found some additional problems with the structure. It should be tied to the value the customer is getting. Ideally, you don’t turn it over after they need it, you turn it over earlier, as Colin said, if that’s valuable to them. And if it’s not valuable to them then maybe you don’t turn it over earlier.

CM: A perfect example of that is a school. I had an example of that with a client recently where they couldn’t turn it over in February, with the manpower and the pace and the flow that they had going for the building, they could have met that, but that didn’t help the school because they were going to make a shift in a February break. So they adjusted their takt and all of their crew sizes down to meet that date that was needed and release that manpower to other projects.

HM: It’s important to note that you don’t establish takt by inspection, you establish takt by policy. You design your production operation or construction operations to meet that takt. Lahey Hospital is a recent example. Lahey was a project performed by Bond Brothers, it was a renovation of space. We decided that every single operation, once we got it back to bare walls, was going to be a one-day operation, and that whatever it was—layout, studs, blocking, pipe, whatever it was that was going to be done for a particular flow unit—was going to be a one-day takt time.

So first, we identified what the work operations would be. We sequenced the work operations, and then we said, “All right, now what would be the crew size that will allow us to do that in a one-day cycle?” I forget how many different handoffs there were, over two-dozen for one of the flow units. We were able to establish a crew size that could do it in a day, and they didn’t have any time left over. The intent is to turn it over to the next performer every day at the same pace.

So Colin, would you like to explain the big benefit of working to a short takt time?

CM: Yeah, absolutely. I’m going to tie this to the first law, Little’s Law (or production law) which you could also think of as a law of batching, or a small batch, or reduce work in process. However it works for you, it’s all basically saying the same thing. What it says is that the smaller the flow unit that you hand off to the next step in the operation, the less your total duration for your project or process will be, so you finish sooner.

And I can give a simple example of that. If we take a five-story building and five trades working their way through, and I define the flow unit as a floor, then I’m going by area here for a moment with a takt of a week, so each trade has a week to move through each floor. And so the first trade is going to finish at the end of week five. The second trade will finish at the end of week six, week seven, week eight, week nine. I have a nine-week schedule.

Without changing the manpower, if this is perfectly balanced, I reduce my takt time to a day. I’m handing off a fifth of a floor every day, my new flow unit is the fifth of the floor, not the whole floor. And I plan my work in such a way that I can release that to the next person, the next day.

I’ve reduced the handoff duration from five days to one day. It’s a four-day savings. Four times four is sixteen days, and nine weeks minus sixteen days is five weeks and four days. To play that out: the first trade finishes at the end of week five, second one finishes at five weeks and one day, two days, three days, four days. There’s the simple math.

The smaller you make your takt, the faster you will finish without increasing manpower, without accelerating, without any of those pieces.

HM: For any given trade, it was a week’s worth of time on the floor. The fifth floor finishes, so they still have five days on the floor, but they hand off to the next trade after one day as opposed to after five days. The first trade finishes on a Friday, the second trade finishes the next Monday, next trade Tuesday, Wednesday, Thursday, and we’re all done in twenty-nine days as opposed to being all done in forty-five days.

It’s a big deal, for a lot of reasons. One of the reasons it’s a big deal is because of general conditions. The general costs of running a project occur over time, based on the amount of time you’re running the project. The CM staff is out there as long as people are building, but if you’re getting done faster, that’s sixteen days from a nine-week schedule.

CM: Yeah, you saved over a third of your time. Your general conditions, the general costs of running the projects, the overhead of running the project, the general administrative costs like keeping track of people on the job—all that stuff, it’s all reduced by a third, and you got the same project done.

You didn’t cut back on any of the value-added steps. By the way, we learned to cut back on the value-added steps when we turn over more often. There are those secondary benefits. But the first order effect is the project is shorter, automatically, and a third shorter is a regular occurrence. And therefore you lower the overhead costs of doing the project, which isn’t value added. None of the work that the CM does is value-added, none of the work that administrative people do is value-added, none of the insurance that you’re paying adds value. But now you’re paying for insurance for two-thirds of the time as opposed to the whole time.

KV: How are you defining value-added?

HM: Anything associated with material in the field is direct value-added. On the flip side, there are three types of waste. Type one waste is anything that’s necessary, but not value-adding, like climbing ladders, getting tools, taking measurements. There are all kinds of things that are necessary but you’re not fabricating, you’re not coding, you’re not installing. There’s a handful of things in the construction world that are value-added, and then there are a lot of things that are enabling. Type one waste is enabling actions.

Type two is basic waste. Moving stuff around that shouldn’t have been there is type two waste. Every time we deliver all of the drywall to a project at once, you know it’s not all installed the next day, so people are moving around to get the drywall, and sometimes moving the drywall because it’s in the way of other work that needs to be done. Type two waste also includes rework, it includes waiting, that sort of thing.

And then type three waste is superfluous work. We coined superfluous work as type three waste. Superfluous waste is waste arising from the management of other work. For example, if you take a really long time answering an RFI. RFI is waste, it’s do-over work, so we count RFI as type two waste. But instead of ask the question, get the answer, we have to put it in writing because we don’t know when we’re going to get the answer. We have to put it in writing, we then have to have a computer system to track it and a workflow to pass it to the right people. All of the work associated with the duration that it takes, and the handoffs, and the approvals, and all that goes along with answering that RFI is superfluous work. If you just answered the RFI, none of that would be needed. And that’s type three waste.

All this waste goes down when you begin taking a takt time approach on projects. Now, I said there’s a secondary effect. Colin, why don’t you speak about how the more frequently we have handoffs, the better the opportunity is for learning?

CM: Each time you make a handoff, it’s an opportunity to have a conversation with the person that you’re handing off to, to evaluate and reflect on whether you did things in the most effective manner? Did you get what you needed? If we only hand off one floor at a time and there was something that didn’t work, one, you have to go back and fix it, which is the failure demand piece, but two, using that same example, each trade only has an opportunity to learn from the previous one what worked for them or didn’t work for them four times because they get handed off five times.

But if we’re handing off a fifth of the floor today, that’s five times five, so twenty-five learning opportunities where we have the conversation that there is in making a promise, right? You have a person who makes the request and the person who makes the promise, and that’s a conversation that occurs. And in that conversation, you can have learning every time the promiser says, “I’m done.” And the requester says, “Thank you. And yes, that was what I asked for.” So, you’ve increased those numbers of conversations by a factor of five, thus increasing the learning opportunity by a factor of five and the opportunity to do something different.

HM: One of the five big ideas is to tightly couple learning with action. Find a way to learn more by doing something and learning from it. Maybe you learn to work in smaller batches. Oh, well what pace should you work at? The fastest pace is not a day, the fastest pace is numerous times within the day.

CM: We were actually on a project, it was a locker room renovation and we did it by stall and it was two hours, and they were turning over one stall at a time to the next trade.

HM: What do we mean by flow unit? Flow unit can be general space, or it could be a room, a system or it could be a stall. In the case of the Lahey project, there were a number of flow units, but the primary flow unit was an examination room. And there were eighty-three or eighty-four exam rooms. The smallest crew that we were going to use was two people and they could do the blocking in seven exam rooms in a day. An exam room was a flow unit and our batch size for the day was seven exam rooms.

CM: I think people get confused when we talk about a flow unit and we describe it as a room or system because they think that all flow units have to be the same, right? A flow unit is a space. It doesn’t matter if it’s the same type of space, all that matters is that the sequence of steps that are going to move through that flow unit and add value to it are the same general sequence of steps. It could be an exam room here, and it could be a nurse’s station there, and it could be an administrative office here, and those are all flow units going through the same process or flow.

Once we’ve defined what the process steps are, as long as those generically repeat as they go through, it doesn’t matter what the nature of the physical space that we’re defining as the flow unit is. What we might call a flow unit or area might be different, but it’s still just the next flow unit.

CM: The second production law, some people call it the law of bottlenecks, or the law of balance, basically says we can only go as fast as the slowest element, so we all should be moving at the same pace through the flow units. Fundamentally, this is the production law that basically says you need takt.

Imagine for a moment as people are moving through a building or moving through the foundation work, if every single step were moving behind at exactly the same pace, both releasing and receiving a work area from the previous step at the same pace, then that release and receive would create a kind of continuous flow. You’re releasing a physical work area that you can’t logistically both work in the same time. As that release and receiving happens at the same time, it creates a force, a metronome step where everybody is moving together. If you’re applying the law of balance, as I’m going to refer to it, you are creating a takt. There’s no way around that, and that’s what we need to acknowledge.

One of the most challenging things though is figuring out in a complex building or whatever else the case may be, how do we achieve that balance in the density of work for every single trip? It requires a lot of thought and a lot of planning up front.

HM: And it can lead to innovation. J.C. Cannistraro, a mechanical contractor that is a Touchplan user, has moved a lot of the fabrication and assembly steps off-site. They’re doing off-site construction. People call it prefabrication, but the general term is off-site construction, so that now the only thing they’re doing when they’re installing the bathroom is they’re bringing in large assemblies that need to be put in place and a couple of connections made as opposed to everything else inside the flow unit.

CM: If you have an activity that is a huge bottleneck, you can gain huge improvement by eliminating it by moving some of the work off-site and outside before the flow unit. And that’s the real advantage of it from a project standpoint of prefabrication as a technique. It’s one of the tools for balancing the work.

HM: A great example of this approach is what the Granger team did on their project for Sparrow Hospital’s pediatric nursing floor. There were two-dozen or so patient rooms, and their batch size was two. Every day, every operation was done in two rooms, but there were a couple of operations that took two crews. It took them all day, one crew all day to get the room done and they had a second crew in the other room all day working on that room. But the commitment was still that we’re turning over two rooms every day to the next group. There was one crew that had half a day’s worth of work in two rooms, and so in the morning, they did their half a day in the two rooms, in the afternoon they went to a different flow unit.

Another example is the Baltimore Harbor Tunnel, there were thirty-two fans that needed to be replaced. They’re allowed to have four fans out of service on each side of the tunnel at a time, so one quarter of the fans could be out of service. They were going to do this as a batch of eight. I said, “No, we’re going to do this as two batches of one, and every week take one off and bring one back on.” It took us five weeks to do it. Their schedule went from four years to two-and-a-half years to do that project by going to much smaller batches.

CM: If every day, everybody is releasing something, it’s much easier to keep track of and manage than many different people having different handoffs.

So let’s talk about the next production law, the law of variation. I’m going to call it the law of reliability to state the goal—we don’t want variation. If we have variation in the steps in the process, we’re going to end up having either work waiting for workers to move into the next step, or workers waiting to move into the next step because it’s not ready, right?

Sometimes people confuse the law of balance to mean the average pace. That’s not what we mean. We mean a definitive pace. If we’re going to have that pulse so that everybody moves together, it can’t have variation. Takt time planning really forces a slightly different way of thinking than some people approach the Last Planner® System. Lots of people have looked at it as, “We’re going to try to continuously remove variation from our system, but we’re going to assume that it exists, so we’re not even going to go for a steady pulse or pace. We’re going to build a bunch of buffers and we’re going to try to slowly improve that to make things better. And we’re going to choose fairly large batch sizes in that because we’re not comfortable with the amount of variation that there is.”

When we take a takt time planning approach, we’re saying that we’re trying to continuously improve to remove variation. We also talk about pull, which is the other thing that I want to mention. Pull is not a production law, it’s a method of control. Pull is how we create signals to only do work at the pace at which the next person needs it. Pull as a control method is there when we assume that variation will occur. It says if one person slows down, we need a mechanism to tell everybody else to slow down with them, right? So that we’re not running into each other. And if one person speeds up, let’s try to speed up together.

HM: Yeah. So Dave, you and I’ve talked about takt planning off and on for over a year now. What questions do you have?

Dave Rolin, Touchplan’s Vice President of Software Products: What do you guys find is the biggest pushback to adopting an approach like this, or why isn’t it an industry standard?

CM: In many cases, because they don’t believe that the possibility of that reliability exists, they still view everything as one of a kind. There’s still this idea that if I stay on the same task for a repeated period of time, I will be more productive and resource-efficient in that sense. But there’s no reason you have to stick your whole crew on one activity at a time. Break it up. But they go to trainings where they’re told, “Keep the crew on the same step one at a time to get your maximum productivity.” And there are still people out there telling them that. And that’s what makes it difficult. There are all these preconceptions that we’re fighting against.

Another factor is that on the CM side, many of them do a terrible job of procurement and make ready planning, and so they inject a ton of variation into the system, which causes the trades to have no faith that they can actually operate on this space.

HM: I’ll add a couple things. Number one is that we really have a lot of resignation about what’s possible with the circumstances today. For the most part, companies are bidding work and they’re making a little bit of money or they lose a little bit of money, and they’re bidding work based on the history of doing work. Well, when you look at the history of doing work, it’s got a lot of waste in it, it’s not reliably managed. There’s nothing like the Last Planner System® going on. There are no practices of making work ready, and so a superintendent’s perspective is that they spent over half of their day every single day following up on what didn’t happen yesterday. And that’s how they understand their job.

Their experience tells them that if they didn’t tell people every day what they need to be doing, that the work wouldn’t get done because people aren’t responsible enough to get it done. But people do want to work reliably, they do want to do the work once, they don’t want to do it over again. They do want to stay busy, they don’t want to be hanging around. They can be trusted. In fact, the trades know more about their work than the superintendent does. We get an immediate improvement as soon as we stop doing three-week look-ahead schedules by the superintendent, and we just do weekly work plans, day-by-day work plans by the foreman.

It’s a kind of systemic resignation, Dave, and it takes a while to open some people up. Their real world is a challenge, it’s an issue about people’s identity. And what we’re doing challenges identity.

 

 

Lean Training: If You Can Increase Project Profitability by 20%, You Can Increase It by 50%

Katherine Van Adzin: Today we’re talking about profit velocity! To start off, could you define what it is?

Continue reading “Lean Training: If You Can Increase Project Profitability by 20%, You Can Increase It by 50%”

BOND Case Study

Read our case study on BOND Brothers, a general contractor based in Medford, Massachusetts, that implemented Touchplan on a recent project for Lahey Hospital’s General Internal Medicine department. Find out how the team overcame a late start and an unexpected change order to finish this complex project five weeks early with money saved.

READ THE CASE STUDY >>